Blue Ridge Road Bike-Ped Project Updates, Winter 2025


Jump To:

 
March 17, 2025 February 28, 2025 January 21, 2025

March 17, 2025

Currently, crews are relocating utilities, both overhead and underground. They are continuing work on the signal installation at the intersection of Westchase and Blue Ridge. Additionally, preparations are underway for the foundation work of the pedestrian bridge, which is expected to be installed later this summer. 

February 28, 2025

Crews are currently completing waterline work, utility relocations, and installing lighting and traffic signals along Westchase Boulevard and Blue Ridge Road. Drivers and pedestrians should continue to watch for work zones and follow posted signs.

January 21, 2025

Due to coordination efforts with NCDOT and private and public utilities, the project is behind schedule. The good news is that crews have resumed work on this exciting project. The contractor has their team working on both the multi-use path and preparations for the installation of the new pedestrian bridge.  

What to expect during construction:

  • Lane closures (between 9 a.m. and 4 p.m)
  • Flagging operations
  • Some weekend work
  • No planned road closures on  Blue Ridge Road

Contact

 

Project Manager
Ben Henderson
ben.henderson@raleighnc.gov 

Project Manager
Stephane Belinga
stephane.belinga@raleighnc.gov 