culvert and stream

Saratoga Headwall Replacement Project

Stormwater System Upgrade

We are replacing the wall at the end of the concrete pipe culvert on Saratoga Drive between Greywood Drive and Old Creek Court.  

The culvert on Saratoga Drive carries water from Beaman Lake into a unnamed tributary to Marsh Creek. 

Project Details

 
Type:
Stormwater
Contractors:
WSP USA Inc.

Contact

 

Amy Billings, PE
Project Manager 

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

The team is working on a solution to repair or replace the downstream endwall on the culvert that runs under Saratoga Drive between Greywood Drive and Old Creek Court. 

The planning for this project includes:

  • Survey work;
  • Utility coordination; and,
  • Structural assessments. 

The project team is considering wingwalls and protection measures to help reduce downstream channel erosion. 

Next Steps

 

Develop design plans

Phase Contacts

 

Amy Billings, PE
Project Manager

Lead Department:
Engineering Services

Schedule
Project Stage  Date
Planning Starts  Winter 2022
Design Complete  Late Summer 2022
Construction Starts Fall 2022
Project Complete Winter 2023