Fire Station three

Safety

Fire Station 3 Replacement

Updating City Facilities

We are replacing and relocating the fire station on South East Street. This station serves eastern and Downtown Raleigh.

The new facility will be on a 1.74-acre site next to the North Carolina Correctional Institution for Women at 1000 Rock Quarry Road. 

Project Details

 
Type:
City Properties and Facilities
Budget:
$11.5 million
Project Lead:
Construction Management
Contractors:
Huffman Architects (Design)

Contact

 

Alexander Shapiro
Project Manager
919-996-5589

 

Lead Department:
Engineering Services
Participating Department:
Fire

Subscribe

 

Programmed

This phase is complete. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Design

The design phase is completed. 
 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Construction

Construction started on October 1, 2024, and is scheduled to last 13 months, with a completion date of November 5, 2025.

Project Update - Spring 2025

The contractor completed under slab electrical and plumbing rough-in and poured the building slab in all areas except the apparatus bay. The concrete and brick installation is about 80% complete.
In the next month, the contractor will work on completing the concrete and brick work, including exterior finishes and installing the roof's steel framing.

Project Update - Fall 2024

The contractor completed site grading, partial installation of retaining walls (3 out of 5), building footing installation, and the water and sewer tie-in. The contractor is now working on the electrical and plumbing rough-ins and building the masonry walls.
 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Schedule

Date Activity
Summer 2021 Project design began
Fall 2022 Project design complete
Summer 2024 Construction bidding
Fall 2024 Project construction begins
Spring 2026 Project construction complete

Related Projects

  All projects