Fire Station three

Safety

Fire Station 3 Replacement

Updating City Facilities

We are replacing and relocating the fire station on South East Street. This station serves eastern and Downtown Raleigh.

The new facility will be on a 1.74-acre site next to the North Carolina Correctional Institution for Women at 1000 Rock Quarry Road. 

Project Details

 
Type:
City Properties and Facilities
Budget:
$11.5 million
Project Lead:
Construction Management
Contractors:
Huffman Architects (Design)

Contact

 

Alexander Shapiro
Project Manager
919-996-5589

 

Lead Department:
Engineering Services
Participating Department:
Fire

Subscribe

 

Programmed

This phase is complete. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Design

The design phase is completed. 
 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Construction

Construction started on October 1, 2024, and is scheduled to last 13 months, with a completion date of November 5, 2025.

Project Update - Spring 2025

The contractor completed under slab electrical and plumbing rough-in and poured the building slab in all areas except the apparatus bay. The concrete and brick installation is about 80% complete.
In the next month, the contractor will work on completing the concrete and brick work, including exterior finishes and installing the roof's steel framing.

Project Update - Fall 2024

The contractor completed site grading, partial installation of retaining walls (3 out of 5), building footing installation, and the water and sewer tie-in. The contractor is now working on the electrical and plumbing rough-ins and building the masonry walls.
 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Schedule

Date Activity
Summer 2021 Project design began
Fall 2022 Project design complete
Summer 2024 Construction bidding
Fall 2024 Project construction begins
Spring 2026 Project construction complete