Fire Station three

Safety

Fire Station 3 Replacement

Updating City Facilities

We are replacing and relocating the fire station on South East Street. This station serves eastern and Downtown Raleigh.

The new facility will be on a 1.74-acre site next to the North Carolina Correctional Institution for Women at 1000 Rock Quarry Road. 

Project Details

 
Type:
City Properties and Facilities
Budget:
$11.5 million
Project Lead:
Construction Management
Contractors:
Huffman Architects (Design)

Contact

 

Alexander Shapiro
Project Manager
919-996-5589

 

Lead Department:
Engineering Services
Participating Department:
Fire

Subscribe

 

Programmed

This phase is complete. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Design

The designer is currently working on Building Permit Review with the City. The Construction Documents were reviewed and approved by Construction Management and the Raleigh Fire Department (RFD) and the Administrative Site Review (ASR) and Site Permits Review (SPR) were successfully completed.

The Art Group meetings, involving the coordination with the designer, RFD and the artist selected for the project, Mr. Maxwell Emcays continue as needed. An art installation will represent the history of African-American firefighters in Raleigh and also link between firefighters and the community they serve.
 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Construction

The project is going to Raleigh City Council for construction bid award approval in August 2024. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Alexander Shapiro

Project Manager

919-996-5589

Lead Department:
Engineering Services

Schedule

Date Activity
Summer 2021 Project design began
Fall 2022 Project design complete
Summer 2024 Construction bidding
Fall 2024 Project construction begins
Spring 2026 Project construction complete