Erinsbrook Park

New Park Implementation

Raleigh Parks from Bond to Beyond Event

Join Raleigh Parks for a family-friendly update on our 23 Parks Bond projects. Discover how the 2022 investment is building healthier neighborhoods and stronger connections across our city.

Thursday, March 26, 4:30 - 7:30 p.m.
Dix Park, Greg Poole, Jr., All Faiths Chapel (1030 Richardson Dr.)
RSVP: lauryn.kabrich@raleighnc.gov

Project Overview

The 2022 Raleigh Parks Bond allocates $6,960,000 for the implementation of the new Erinsbrook Park. Erinsbrook Park will be located at 11921 Leesville Road in Raleigh. The 13-acre site is mostly wooded and bisected by a stream, that is a major feature of the site.

In 2017, the City Council adopted the Erinsbrook Park Master Plan. Park implementation will follow the adopted master plan. Per the master plans, site elements include a parking lot, playground, open lawn area, picnic shelters, restroom facility, trails, stormwater treatment features, and EV charging stations. 

Please see the Resources section at the bottom of this page to download the Master Plan. 

Project Timeline: 2024-2027

Interactive Map of Park Projects
2022 Parks Bond Spending Tracker
List of Park Project

Project Details

 
Type:
Parks
Budget:
$6,960,000 (2022 Parks Bonds funding)
Contractors:
Benesch (Civil and Landscape Architect consultants)

Upcoming Events

 
  • Mar
    26

    Raleigh Parks from Bond to Beyond

    4:30 p.m. • Thursday
    Dorothea Dix Park
    Add to Calendar 2026-03-26 16:30:00 2026-03-26 19:30:00 Raleigh Parks from Bond to Beyond Dorothea Dix Park 1030 Richardson Drive Raleigh, NC 27603 City of Raleigh America/New_York public

Contact

 

Engagement
Di Gao
Di.Gao@raleighnc.gov
919-996-4783

Design and Construction
Dale Tiska
Dale.Tiska@raleighnc.gov
919-996-3541

Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Engineering Services
Service Unit:
Parks

Subscribe

 

Planning

No planning phase involved in this bond project. Park Master Plan was adopted by the City Council in 2017.

Design

The design will occur from 2024 to 2026.  In 2024-2025, Raleigh Parks will perform additional community engagement to transition the park design from the 2017 master plan to the final park plans. 

City Council approved the Schematic Design on June 3, 2025.

Construction

Construction is planned for 2027-2028.

Complete

Project completion and park opening are planned for 2028.


Erinsbrook Park Location

map of erinsbrook

Map of the location for the future Erinsbrook Park. 

Project Schedule

Date Activity
2024 - 2025 Site Analysis, Schematic Design, and Community Engagement
2025 - 2026 Design Development, Construction Documents design, and Permitting
2027 - 2028 Site Construction (planned)

Public Participation Process

The public process for Erinsbrook Park project followed the Consult pathway, as outlined in the City of Raleigh Public Participation Playbook.