Stormwater Drain

Stormwater

City-Wide Lining and Pipe Rehabilitation Project

Stormwater Improvements

The City of Raleigh has compiled a list of eight locations where drainage infrastructure requires evaluation and repair.  Six of those locations are stormwater system repair projects and two locations are drainage assistance projects.

Project Details

 
Type:
Stormwater
Budget:
$300,000
Project Lead:
Stormwater Management
Contractors:
Kimley Horn (Design); Applied Polymerics, Inc. (Construction)

Contact

 

Erik Mayr, PE
Project Manager
erik.mayr@raleighnc.gov
919-996-4077

Lead Department:
Engineering Services

Subscribe

 

Planning

Raleigh Stormwater obtained survey data and video footage of the stormwater systems. The final recommendations will be used to design infrastructure and repairs at the nine project locations.

Lead Department:
Engineering Services

Design

This phase is complete. The engineered material used in the lining process is expected to have a long-life expectancy and has proven to be less costly and less disruptive than pipe replacement. This work will extend the life of the existing stormwater system.

Lead Department:
Engineering Services

Construction

The table below provides detailed information about the design and construction for each location.

System Repairs

Construction to begin in Summer 2025 and be completed by Fall 2025.

Drainage Assistance

Construction schedule TBD for the Drainage Assistance projects.

What To Expect

Work hours will be Monday - Friday from 8:00 a.m. to 5:00 p.m., with no work scheduled on the weekend, except in an emergency or with prior approval from the City. Residents will be notified if such schedule changes need to take place. We do not anticipate needing to close the road to through traffic.

We anticipate some flagging and light traffic control for operations primarily related to the liner delivery and installation. Local traffic (residents within the work zone) will have access to their driveways and will be able to come and go as needed. Please don’t park on the street within and near the construction area for the duration of construction.

Lead Department:
Engineering Services

Project Locations

The following projects are separated into the System Repairs or the Drainage Assistance Program (DA).

Project NumberLocationDescriptionTypePhase
1Everett AvenueLine 50 linear feet of the existing storm drain system pipes under and along Everett Ave. System RepairsConstruction Coming Soon
2Pineview StreetLine 365 linear feet of the existing storm drain system pipes under and Pineview Street from Jarvis Street to Williamson Drive. System RepairsConstruction Coming Soon
3Scotland StreetLine 20 linear feet of the existing storm drain system pipes along Lassiter Mill Road.System RepairsConstruction Coming Soon
4Forsyth StreetLine 65 linear feet of the existing storm drain system pipes under Forsyth Street and two properties east of the intersection with Granville Drive.System RepairsConstruction Coming Soon
5Burkwood LaneLine 140 linear feet of the existing storm drain system pipes between 100 and 104 Burkwood Lane.System RepairsConstruction Coming Soon
6Tollington DriveLine 500 linear feet of the existing storm drain system pipes along Tollington Drive.System RepairsConstruction begins June 2025
7Crandon LaneLine 400 linear feet of the existing storm drain system pipes under Crandon Lane at Forham Lane, and between 3200 and 3120 Crandon Lane.DADesign
8Fairlie PlaceLine 300 linear feet of the existing storm drain system pipes between Fairlie Place and North Exeter Way. Drainage structures will be repaired and sink holes filled in. DADesign

Locations of Lining Projects

For a full screen view, visit the Stormwater Pipe Lining Projects GIS Map.

Learn about the Types of Repairs

CIPP Lining

A cured-in-place pipe lining is a trenchless pipe repair method that adds pipe lining within an existing pipe.

Video of CIPP repair provided by Pipelining Technologies.

The Trenchless Pipelining Process Explained (C.I.P.P.)