Cheswick Drive Bridge Replacement Project

Improving mobility and connectivity for pedestrian, bicycle, and vehicular traffic

The goal of the project is to replace the aging Cheswick Drive bridge with a safer, more reliable structure for the community. The new bridge will continue to provide access for vehicles and pedestrians. Because the bridge is the only access point for several nearby homes, construction will be carefully planned to maintain access for residents while minimizing impacts to the surrounding area.

Project Details

 
Type:
Transportation Improvements
Budget:
Design - 614,500
Project Lead:
Roadway Design & Construction
Contractors:
Design - RK&K

Contact

 

Project Manager 
Keith Tew
Keith.Tew@raleighnc.gov 

Division Manager
Sylvester Percival
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

The project is currently in the design phase. Design is anticipated to be complete in fall 2027. Additional project milestones and construction information will be shared as they become available.

Lead Department:
Engineering Services

Project Schedule

DateActivity
Winter 2025Start Design
Fall 2027Finish Design
Spring 2028Advertise for Construction Bids
Summer 2028Start Construction
Summer 2029Finish Construction

Project History

bridge

The existing Cheswick Drive bridge was built in 1960 and has served the community for more than 60 years. During a 2018 inspection, the bridge was found to be in poor condition due to age and deterioration. Temporary repairs were recommended to keep the bridge safe while plans for a long-term replacement moved forward. 