Parks and Recreation

Leesville Community Park and Strickland Road Park

Improvements

Construction for both Leesville Community Park and Strickland Road Park will begin on April 28, 2025, and is expected to continue through January 2026. Both parks will be closed during the construction period. The Leesville Community Library will remain open, and public parking will still be available. Please see below for more detailed closure information for each park.

Project Overview

The 2022 Raleigh Parks Bond allocates $2,000,000 to improve Leesville Community Park and Strickland Road Park. Proposed site improvements at both parks include permanent restroom facilities and improved amenities.

Leesville Community Park is an existing 56-acre neighborhood park located on Country Trail in northwest Raleigh. The Leesville Community Park Master Plan was adopted in May 2007.  Proposed improvements include playground expansion with shade structure, new restroom building, outdoor reading nook, and electric vehicle charging stations.

Strickland Road Park is an existing 36-acre neighborhood park located on Strickland Road in northwest Raleigh.  Proposed improvements include a new restroom building, an accessible paved path and overlook area, a parking lot, stormwater improvements, new playground surfacing, and electric vehicle charging stations. 

Project Timeline: 2024-2026 

Interactive map of Park Projects
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$2,000,000 (2022 Parks Bonds funding)
Contractors:
WithersRavenel (Civil and Landscape Architect consultants)
Lead Department:
Parks, Recreation and Cultural Resources
Service Unit:
Parks

Subscribe

 

Planning

No planning phase is involved in this bond project.

Design

The Schematic Design was approved by the Parks, Recreation and Greenway Advisory Board in February 2024.

Construction

Construction for both Leesville Community Park and Strickland Road Park commences in Spring 2025. Construction is expected until end of 2025. 

  • For Leesville Community Park, the library and most of the parking lot will remain open during construction.  Construction will mainly take place around the restroom building and playground. These areas will be closed for public use during construction.
  • For Strickland Road Park, the entire park will be closed for most of the construction timeline, including the parking lot, playground, and trails.

Complete

Project completion and park opening are planned for 2026.


Project Schedule

Date Activity
2023 - 2024 Public Engagement and Schematic Design
2024 - 2025 Design Development, Construction Documents, and Permitting
2025 - 2026 Site Construction

Public Participation Process

The public process for the Leesville Community Park and Strickland Road Park project followed the Inform pathway, as outlined in the City of Raleigh Public Participation Playbook, and concluded with the Parks, Recreation and Greenway Advisory Board approval of the Schematic Design in February 2024.