Exterior shot of the Green Road Park community center building

Parks and Recreation

Green Road Park

Improvements

Project Overview

The 2022 Raleigh Parks Bond allocates $4,470,000 for site improvements to Green Road Park. Improvements focus on park accessibility and safety enhancements, replacement of the existing restroom building, existing site renovations, and new recreational features.

Green Road Park is an existing 29-acre park located at 4201 Green Road in northeast Raleigh.  Current facilities include a community center, restroom building, baseball fields, sand volleyball courts, tennis courts, and a playground.  The park shares space with Wake County’s Green Road Community Library.

Proposed site improvements include new accessible pathways connecting park features; raised parking lot crosswalks to improve pedestrian safety; entrance plaza with shade structure; expanded playground; adult fitness area; new restroom building; futsal and pickleball courts; site drainage improvements; electric vehicle charging stations; stormwater improvements; and public art installation.

In May 2024, the Parks, Recreation and Greenway Advisory Board approved the Green Road Park schematic design plans. The project is currently in the final design and permitting phase with construction planned for 2025.

Please visit the engagement portal to view the public engagement process. Please see the Resources section at the bottom of this page for project documents.

Project Timeline: 2024-2027

Interactive map of Park Projects
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$4,470,000 (2022 Parks Bonds funding) and $250,000 (Public Art funding)
Contractors:
CLH design, p.a. (Civil and Landscape Architect consultant)
Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Parks, Recreation and Cultural Resources
Service Unit:
Parks

Subscribe

 

Planning

No planning phase involved in this bond project.

Design

The Schematic Design was approved by the Parks, Recreation and Greenway Advisory Board in May 2024.

Construction

Construction is planned for 2025-2027.

Complete

Project completion and park opening are planned for 2027.


Project Schedule

Date Activity
2023 - 2024 Public Engagement and Schematic Design
2024 - 2025 Design Development, Construction Documents, and Permitting
2025 - 2027 Site Construction (planned)

Public Participation Process

The public process for the Green Road Park project followed the Involve pathway, as outlined in the City of Raleigh Public Participation Playbook, and concluded with the Parks, Recreation and Greenway Advisory Board approval of the Schematic Design in May 2024.

Related Projects