Glenwood Creston Drainage Project Construction
Stormwater System Upgrade
Updated: Aug 22, 2025 - 12:56 pm
We started construction for the Glenwood Creston Drainage Project and anticipate it being complete in November 2026. This project will be completed in phases so actual construction activities will vary along the project corridor which starts upslope of Woodland Avenue and terminates downslope of Alexander Drive.
What To Expect
Traffic closures will range from flagging and light traffic control to temporary lane or street closures. For the most part, local traffic (residents within the work zone) will have access to their driveways and will be able to come and go as needed. Normal work hours will be Monday - Friday from 7:30 a.m. to 6:00 p.m. No work will be scheduled on weekends or City holidays, except in an emergency or with prior approval from the City. The City will have an inspector onsite daily.