New stormwater pipe running under Galahad Drive

Stormwater

Galahad Drive Stormwater Pipe

Emergency Repair

We made emergency repairs to a stormwater pipe that failed on Galahad Drive between Luther Road and West Campus Drive. This stormwater project was completed in December 2020.

Project Details

 
Type:
Stormwater
Budget:
$203,870
Project Lead:
Stormwater Management
Contractors:
Carolina Civilworks

Contact

 

Todd Rall
Project Manager
todd.rall@raleighnc.gov
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete. 

Phase Contacts

 

Gilles Bellot, PE

Project Manager

919-996-4001

Lead Department:
Engineering Services

Construction

This phase is complete. 

Phase Contacts

 

Todd Rall

Project Manager

919-996-4006

Lead Department:
Engineering Services

Complete

We completed emergency repairs to the stormwater pipe on Galahad Drive. Work included: 

  • Installing a new pipe;
  • Stabilizing the area around the pipe; and, 
  • Paving the road. 

The road reopened in December 2020. 

Phase Contacts

 

Todd Rall

Project Manager

919-996-4006

Lead Department:
Engineering Services

New stormwater pipe that runs under Galahad Drive. 

Stormwater pipe on Galahad Drive before emergency repair.

Schedule

Date Activity
October 2020 Stormwater pipe failed; emergency repairs required
October - December 2020 Repairs completed