- Pre-construction meeting
- A Pre-construction Meeting must be requested 5 (five) business days prior to the beginning of work.
- It can be held either virtual or in person.
- Consult with your Inspections Coordinator.
- Checklist Placeholder
- During Construction
- Keep the current City-approved plans and all permits at the job site.
- Submit inspection requests by 3 p.m.
- Add the right contacts and give clear details about the work that is ready.
- Any changes to the plan must be communicated to the inspector.
- Changes can be Field Revisions or may require Plan Revisions.
- Checklist Placeholder
- As-Built Submittals
- Submit full As-Built documents for water and sewer to: DSAsbuiltSubmittals@raleighnc.gov and the Coordinator.
- Sanitary sewer CCTV Inspection
- When sewer as-builts are received, the Coordinator will request the CCTV Inspection with Raleigh Water.
- Stormwater As-built Submittals and CCTV Inspections
- Submit full As-Built documents for storm infrastructure
- Process page - Stormwater Conveyance Permit | Raleighnc.gov
- Pre-Warranty and Acceptance process
- All inspections and as-built submittals must be completed.
- Warranty Period
- The 1 (one) year warranty period begins when all work necessary is completed.
- A final walk-through must be completed and any issues addressed prior to the end of the one-year period to begin the acceptance process.
- Acceptance
- Acceptance letters are prepared and provided to the permit holder.
- Acceptance letters are required for any reimbursement request, where applicable.