Certificate of Occupancy

How to apply for a partial or temporary certificate of occupancy.


Jump To:

 
How to Get a Certificate of Occupancy

A Certificate of Occupancy (CO) is issued when a building has passed all inspections and is ready for use. A new building cannot be legally occupied until a CO has been issued.

A CO is issued same day for a new building, addition, change or use and interior completion.  A Certificate of Completion (CC) is issued by the next day for alterations/repairs. You can view your CO or CC via the permit portal from the building permit, within the attachment tab.

How to Get a Certificate of Occupancy

  1. Complete Construction and Required Systems
    Ensure the building and all required systems like building, plumbing, mechanical, electrical, fire protection, and gas, are completed to the point where they can be inspected before concealed.
  2. Final Inspections
    Inspection staff conducts the final inspections of the building and all service systems.
  3. Issuance of Certificate of Compliance
    Once plumbing, electrical, mechanical, fire protection, or gas is finished and passes inspection, the inspections staff issues a certificate of compliance. This certificate confirms that the work is complete. For some permits, it allows the system to be connected to utilities. It does not give permission to occupy or use the building.
  4. Issuance of Certificate of Occupancy (CO)
    After satisfactory completion of the building and after all required inspections are passed, the inspection staff may issue a Certificate of Occupancy.
    A building cannot be occupied until the Certificate of Compliance has been issued.
  5. Temporary or Partial Options (If Necessary)
    TCO/TCOC (Temporary Certificate of Occupancy/Temporary Certificate of Compliance)
    1. May be issued for specific portions of a building deemed safe for occupancy.
    2. Must be reapplied for every 30 days, for a maximum of 180 days.
    3. A new submittal is required after 180 days.
    4. If a TCO/TCOC exceeds 180 days with no action, the contractor is in violation, and utilities may be terminated.
    5. Not allowed for residential occupancies if dwelling unit work is incomplete.
  6. PCO/PCOC (Partial Certificate of Occupancy / Compliance) 
    Can be issued to allow occupancy of portions of a building that are fully complete and will not require additional inspections.
  7. Certificate of Occupancy
    Once all portions of the project meet code requirements and all inspections are fully released, the inspection staff may issue the final Certificate of Compliance, and the building can be fully occupied.

Back to 8 Stages of Development

Contact

 

Planning and Development
Customer Service Center

Need Help?
Use Ask Raleigh

Permit Helpline
919-996-2500

Subscribe

 
Lead Department:
Planning and Development
Service Categories:
Permits - ResidentialPermits - Commercial
Scroll to top