People walking on the greenway trail

Parks and Recreation

Crabtree Creek Improvements at Raleigh Boulevard

New trail construction

A section of the Crabtree Creek Trail between N. Raleigh Blvd and Crabtree Blvd, between mile markers 51/4 and 6 experienced stream bank erosion causing the need for repairs. The realigned section of the trail parallels an existing sewer easement through a wooded area and rejoins the existing path. A second section of the trail has been relocated away from the stream bank and also parallels the sewer line.

Project Details

 
Type:
Greenways and Trails
Contractors:
Stantec Consulting Services, Inc. and Troy Hutchins Construction, LLC

Contact

 

Construction
Engineering Services
Jay Shah, Engineer
jaykumar.shah@raleighnc.gov

Engineering Services
Ben Possiel, PE, Engineering Supervisor
Benjamin.possiel@raleighnc.gov

Design
Raleigh Parks 
David Bender, Engineer
david.bender@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural ResourcesEngineering Services

Subscribe

 

Design

The consultant design team has completed a 100% version of construction documents have resubmitted for final permit approval. Once the final construction plans and permits have been approved, the project will be publicly bid for construction.

Phase Contacts

 

Raleigh Parks 
David Bender, Engineer
david.bender@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources

Construction

The project is now complete. This project began in July 2023 and was anticipated to be completed in Spring 2024. However, multiple weather events have contributed to completion delays. Like a majority of trail sections, this trail section is also located in a floodplain. Floodplains are prone to flooding and designed to carry floodwaters. Due to permit restrictions, grading elevation changes were limited to prevent unintended flood impacts. Within these constraints, we collaborated with the contractor and design consultant to incorporate shallow ditches (or swales) where possible, providing some water capacity relief for the asphalt trail during heavy rain events.

Many of our greenway projects are built within relatively narrow corridors to minimize disturbances to natural surroundings and reduce environmental impacts. Construction is highly dependent on dry conditions, as critical tasks such as grading, subgrade installation, and asphalt placement require stable ground. These challenges are even greater in flood-prone areas, such as this project.

A significant setback occurred in late 2023 when a major weather event caused the creek to rise rapidly, overtopping the silt fence and depositing substantial sediment onto the project site. This required coordination with permitting agencies for proper cleanup, regrading, and streambank assessment, as the storm had altered the bank’s structure. The necessary redesign and permitting for bank repairs contributed to project delays.

Phase Contacts

 

Engineering Services
Jay Shah, Engineer
jaykumar.shah@raleighnc.gov

Engineering Services
Ben Possiel, PE, Engineering Supervisor
Benjamin.possiel@raleighnc.gov

Lead Department:
Engineering Services

Complete

The project is now complete and open for public use.


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

DateActivity
December 2022Complete design and permitting
February 2023Advertise for construction
Mid to Late July 2023Start of construction
February 28, 2025Construction completion