Jump To:
March 13, 2025
Hargett Street Lane Closure
Beginning Monday, March 17, the City of Raleigh will implement a westbound lane closure on Hargett Street between McDowell Street and Dawson Street to accommodate the crane operations and install pre-cast panels for the new Raleigh City Hall construction. The closure will remain in place through December 31, 2025.
In the next few weeks, crews will start installing the building’s façade. This process will require the closure of a section of Hargett Street. This closure will facilitate the continuous concrete pour required to build out the building’s floors and place the building façade. Additionally, multiple concrete trucks and equipment will be staged within the closure area for efficient material and equipment unloading.
March 27, 2025
In recent weeks, the construction site has seen a lot of action. The construction contractor has many crews working on different parts of the building. They have also revised the construction schedule, so work occurs almost around the clock. The building's shell is primarily made of concrete reinforced with rebar. Part of the concrete placement process uses a machine called a boom pump.