April 1, 2025
Construction activity in March
In the last 30 days, the construction site has been busy, and the crews are making a lot of progress. Crews have finished the second level floor and columns, and shear walls are being prepped and poured.
What is a Shear Wall
A shear wall is a wall that is designed and constructed to resist racking or shaking from forces such as wind. They are built using concrete and cold-formed steel. Shear walls significantly reduce the sway of a structure.
What to expect in the next 30 days
The team is currently working on the level three floor. They are installing the rebar supports, and concrete crews will pour the level three floor soon. Once the concrete team pours the floor, a crew will start prepping the level 3 walls and columns for concrete. From there, the team will start the prep work for the level 4 floors.