City Hall Update, April 2025


Jump To:

 
April 1, 2025 April 16, 2025

April 1, 2025

COnstruction site image of City Hall shows boom pumps placing concrete on level 3.

Construction activity in March

In the last 30 days, the construction site has been busy, and the crews are making a lot of progress. Crews have finished the second level floor and columns, and shear walls are being prepped and poured. 

What is a Shear Wall

A shear wall is a wall that is designed and constructed to resist racking or shaking from forces such as wind. They are built using concrete and cold-formed steel. Shear walls significantly reduce the sway of a structure.

What to expect in the next 30 days

The team is currently working on the level three floor. They are installing the rebar supports, and concrete crews will pour the level three floor soon. Once the concrete team pours the floor, a crew will start prepping the level 3 walls and columns for concrete. From there, the team will start the prep work for the level 4 floors.  

April 16, 2025

With all the construction progress, the City Hall construction team thought it was time for another time-lapse video. Watch the below time-lapse video and check out all the progress the construction team has made since February.  

Raleigh's New City Hall - Construction Video February 12 - April 15, 2025