Project Timeline Details on what's happening at the former DMV site Updated: Jul 24, 2025 Jump To: Tentative Schedule and Completed Milestons Tentative Schedule and Completed Milestons We are making significant progress on the demolition of the DMV building. The demolition & abatement contract was approved by Council May 20, 2025.SUMMER 2024 - COMPLETEProject investigation and abatement designSPRING 2025 - COMPLETEPermitting began Early 2025. Permit review occurred through March 2025.Bidding began in Spring 2025We received quotes from qualified demolition companiesSUMMER 2025 - 2026City Council approval May 20, 2025An RFP for a Market Study was sent out to help support the project. A consultant should be chosen this Summer. Contract negotiations, routing and execution is anticipated through June 2025Safe removal of all site materials and deconstruction of all structures will happy - known as “remediation”: approximately one yearThe site will be ready for re-use Summer of 2026. Additional Information City's Journey to Acquisition Project Page: Former DMV Site Back to Community Department: Community Engagement Subscribe Enter your email to view all topics Was this page helpful? Yes No Email Please choose the type of issue you are experiencing with the page from the dropdown. - Select -Accessibility IssueMissing informationWrong informationDesign issueSomething isn’t working as expectedCustomer Service issue (Examples: trouble with paying utility bill, missed garbage collection, permit issues, etc.) Comments Would you like to be notified by the City about your feedback? This feedback widget is not intended for customer service issues. This feedback is reviewed monthly to help us improve our site. For immediate customer service please refer to our staff directory.