Project Timeline

Details on what's happening at the former DMV site


Jump To:

 
Tentative Schedule and Completed Milestons

Tentative Schedule and Completed Milestons

We are making significant progress on the demolition of the DMV building. The demolition & abatement contract was approved by Council May 20, 2025.

SUMMER 2024 - COMPLETE

  • Project investigation and abatement design

SPRING 2025 - COMPLETE

  • Permitting began Early 2025. Permit review occurred through March 2025.
  • Bidding began in Spring 2025
  • We received quotes from qualified demolition companies

SUMMER 2025 - 2026

  • City Council approval May 20, 2025
  • An RFP for a Market Study was sent out to help support the project. A consultant should be chosen this Summer.
  • Contract negotiations, routing and execution is anticipated through June 2025
  • Safe removal of all site materials and deconstruction of all structures will happy - known as “remediation”: approximately one year
  • The site will be ready for re-use Summer of 2026.