Raleigh Blvd Trail Realignment and Relocation Project

New trail construction

A section of the Crabtree Creek Trail between N. Raleigh Blvd and Crabtree Blvd (between mile markers 5 ¼ and 6) has experienced stream bank erosion causing the need for trail repairs. The section of trail will align through a wooded area parallel to an existing sewer easement and rejoin the existing path east of mile marker 5½. A second section of the trail, west of mile marker 5 ¼,  will be relocated away from the stream bank and parallel to the existing sewer. This section of Crabtree Creek Trail will be closed during construction, however, a detour will be provided utilizing Remington Rd, Marlborough Rd, Rumson Rd, Barksdale Dr, and N Raleigh Blvd. There are no sidewalks along Barksdale Rd and a portion of Remington Rd, therefore pedestrian access is limited.  

Project Area Map

Project Details

 
Type:
Greenways and Trails
Contractors:
Stantec Consulting Services, Inc. and Troy Hutchins Construction, LLC

Contact

 

Construction Project Manager
Jay Shah
jaykumar.shah@raleighnc.gov

Construction Supervisor
Ben Possiel, PE
Benjamin.possiel@raleighnc.gov

Design Project Manager
David Bender

Lead Department:
Parks, Recreation and Cultural ResourcesEngineering Services
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The consultant design team has completed a 100% version of construction documents have resubmitted for final permit approval. Once the final construction plans and permits have been approved, the project will be publicly bid for construction.

Construction

Construction is expected to begin on Monday, July 10, 2023. While in construction this section of Crabtree Creek Trail is closed. A detour map is shown below. The detour utilizes Remington Rd (sections with no sidewalk), Marlborough Rd, Rumson Rd (no sidewalk), Barksdale Dr, and N Raleigh Blvd.

detour map for Raleigh Blvd greenway trail. Detour shown is Remington Rd to Marlborough Rd to Rumsome Rd.

Phase Contacts

 

Construction Project Manager
Jay Shah
jaykumar.shah@raleighnc.gov

Lead Department:
Engineering Services

Complete

Phase details coming soon.


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

Date Activity
December 2022 Complete design and permitting
February 2023 Advertise for construction
Mid to Late July 2023 Start of construction
Spring 2024 Estimated construction completion. Please note when we have a more specific date, this will be updated.