Burgess Court Pipes

Stormwater

Burgess Court Pipe Stabilization

Minimizing Erosion

We stabilized the stormwater pipes that run under Burgess Court. The project will help stop the erosion and stabilize the pipe inlet.

Project Details

 
Type:
Stormwater
Budget:
$280,000
Project Lead:
Stormwater Management
Contractors:
Timmons Group (Design) - RES Carolina’s (Construction)

Contact

 

Dan Clinton, PE
Senior Engineer
dan.clinton@raleighnc.gov
919-996-4003

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Construction

This phase is complete.

Next Steps

 

The team is expected to start construction on the project in August 2022.

Lead Department:
Engineering Services

Complete

The two large corrugated metal pipes that allow stream flow to go under Burgess Court were damaged resulting in significant erosion. We completed the construction of a concrete headwall at the entrance of the pipes to stabilize the pipe and stop erosion.

Lead Department:
Engineering Services

Burgess Court Pipes Before Construction

Burgess Court Pipes During Construction

Burgess Court Pipes After Construction

Schedule

Date Activity
Fall 2019 Project Identified
Fall 2020 Preliminary Design Completed
Spring 2021 Easement Acquisition Completed
Fall 2022 Design Completed
Summer 2022 Construction Begins
Winter 2022 Construction Completed