Shows a section of Raleigh Blvd that the City is getting ready to install sidewalk on.

Transportation

Garner Road Pedestrian Improvements

We are making sidewalk and pedestrian improvements!

The improvements on Garner Road are expanded across multiple intersections along the corridor, including Bragg Street, McMakin Street, Hoke Street, Saints Avenue, and Peterson Street, and connect to the Walnut Creek Trail. 

The scope includes installation of concrete sidewalks, concrete curb ramps, asphalt multi-use path connecting to the Walnut Creek greenway, monolithic concrete islands, signing and pavement markings, and traffic signal improvements at Bragg Street.  

Project Details

 
Type:
Sidewalks
Contractors:
Roadway Design & Construction

Contact

 

Project Manager
Stephane Belinga
stephane.belinga@raleighnc.gov 

Division Manager
Sylvester Percival, PE
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering ServicesTransportation
Service Unit:
Mobility Strategy and Infrastructure

Subscribe

 

Planning

If you have any questions or comments pertaining to this sidewalk petition or planning process please feel free to contact us via e-mail at Petition.Specialist@raleighnc.gov or by calling (919) 996-4054.

Lead Department:
Transportation

Design

Design Update August 2024

The design team completed the advanced design plans and they are being reviewed by the City's Development Services.

We are in the design phase of the project.

Proposed design includes:

  • Sidewalk installations
  • Pedestrian crossings
  • Pedestrian refuge islands
  • Crosswalk installations
Lead Department:
Engineering Services

Construction

Construction Updates

July 17, 2026

Construction crews are relocating overhead utility lines, pouring concrete for pedestrian refuge islands and the remaining curb ramps at the South Bragg Street and Garner Road intersection, and preparing to install the new multi-use path. The project team is also coordinating remaining utility work along the corridor.

June 15, 2026

The contractor is pouring new sidewalk and curb ramps between Peterson Street and Hoke Street to improve pedestrian access along the corridor. The project team is also coordinating utility work and working with Raleigh Transit to relocate a bus stop sign near McMakin Street.

May 15, 2026

The construction team is coordinating with private utility companies to relocate utilities along the project lines. 

April 1, 2026

On Tuesday, Dec. 2, the Raleigh City Council awarded the construction contract for the Colleton Road Sidewalk Project and Garner Road Pedestrian Improvements to Lanier Construction Company for $1,032,640.

Lead Department:
Engineering Services

Project Schedule

DateActivity
Fall 2024Complete Final Designs
Winter 2026Advertise for Construction Bids
Spring 2026Start Construction

Related Projects

  All projects