Walnut Creek Pump Station Odor Control

Update: Construction contract awarded to Water & Waste Systems. 

_________________

The existing odor control equipment is outdated and not performing sufficiently. The removal and replacement of this outdated equipment is scheduled to take place during the life of this project. Two new bio-towers and one new carbon scrubber will be installed. The two bio-towers are filled with a foam substance. Air is pulled into the towers and across this substance to remove odor. This air is then moved through a carbon scrubber for added odor control. Additionally, the project construction will add new duct-work and covers.

 

Project Details

 
Type:
Water and Sewer
Budget:
$2,900,000
Contractors:
Freese & Nichols

Contact

 

Matthew Cotton, PE
Senior Project Administrator
Email
Phone: 919-996-3528 (Office)
Office Location: 1 Exchange Plaza #620
Raleigh, NC 27601

Lead Department:
Water

Pre-Approval

This phase is complete.

Lead Department:
Water

Programmed

This phase is complete.

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

Project currently under design with Freese & Nichols at 75 percent stage. Soil work conducted at pump station by consultant.

Lead Department:
Water

Right of Way Acquisition

Phase details coming soon.

Lead Department:
Water

Construction

Phase details coming soon.

Lead Department:
Water

Complete

Phase details coming soon.

Lead Department:
Water

History

The Walnut Creek Pump Station Odor Control project is part of the Capital Improvement Program. A recent study shows that the existing odor control equipment is no longer effective. These improvements will help raise the comfort level of local residents.

Schedule

Date Activity
Summer 2019 Project Design Complete
N/A Permitting Complete
N/A Easement Acquisition Complete
Summer 2019 Project Bid Complete
Winter 2020 Project Construction Begins
Summer 2020 Project Construction Complete