Pine Hollow

Elevated Water Storage Tank

This project will include the installation of a new 500,000 gallon water storage tank off Leesville Church Road. This installation will improve system reliability and water age in that pressure zone. The existing Springdale Tank will be taken out of service with demolition of the tank scheduled during the project.

 

Project Details

 
Type:
Water and Sewer
Budget:
$2,900,000
Project Lead:
Matt Cotton, PE
Contractors:
Public Utilities Capital Improvement Program

Contact

 

Matthew Cotton, PE
Senior Project Administrator
Phone: 919-996-3528 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Pre-Approval

This phase is complete.

Lead Department:
Water

Programmed

This phase is complete.

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

 

  • Design stage is complete.
  • Final approval in process.
  • Project is expected to bid to Contractors in May 2019.
  • Bid opening in August 2019. 
Lead Department:
Water

Right of Way Acquisition

Phase details coming soon.

Lead Department:
Water

Construction

Construction is underway and the contractor is Maguire Iron. Tank structure was built in late September 2020. Welding will continue through October and November 2020, with the tank scheduled for inside and outside painting in December 2020. The tank will then be filled, tested, and tied into the distribution system. The tank should be online and in service in January 2021.

Pine-Hollow-Water-Tank-Crane

Crews prepare to place water tank on completed water tank structure.

Pine-Hollow-Water-Tank-Crane

Crews place completed water tank on water tank structure.

Lead Department:
Water

Complete

Phase details coming soon.

Lead Department:
Water

History

Project was bid to contractors in Spring 2019. This will be a new elevated tank which will take the place of the existing Springdale Tank. The new tank will be called Pine Hollow which is the name of the nearby middle school. Increase tank volume will improve reliability and water pressure. The tank structure is being built and should be in place by Fall 2020.

Schedule

Date Activity
Summer 2019 Project Design Complete
Spring 2019 Permitting Complete
N/A Easement Acquisition Complete
Summer 2019 Project Bid Complete
Summer 2020 Project Construction Begins
Winter 2021 Project Construction Complete