2015 Waterlines Project 1

UPDATE: The construction contract for this project was awarded to the lowest responsible bidder, Park Construction.  Construction will begin late this fall.  Residents will be notified at least fifteen (15) days before construction begins in their area.

The purpose of this project is to replace approximately 13,700 linear feet (LF) of 6-inch, 8-inch, and 12-inch water main. Project will rehabilitate or replace approximately 2,000 linear feet of 8-inch gravity sewer lines. Three project areas in the north of Raleigh city limits are covered. Area 1 focuses around the intersection of Leesville Road and O’Neal Road. Area 2 is located by the intersection of Falls of the Neuse Road and Harps Mill Road. Area 3 is located by the intersection of Millbrook Road and Six Forks Road.

 

Project Details

 
Type:
Water and Sewer
Budget:
$3,000,000
Contractors:
Park Construction

Contact

 

Julie Parham, PE

Senior Project Manager

Email

919-996-4541 (Office)

1 Exchange Plaza #620
Raleigh, NC 27601

 

- OR -

 

Breanne Long, PE

Senior Project Manager

Email

919-996-3732 (Office)

1 Exchange Plaza #620
Raleigh, NC 27601

Lead Department:
Public Utilities

Pre-Approval

This phase is complete.

Lead Department:
Public Utilities

Programmed

This phase is complete.

Lead Department:
Public Utilities

Planning

This phase is complete.

Lead Department:
Public Utilities

Design

This project was advertised for construction bids on Friday, May 10, 2019.  A pre-bid meeting scheduled for 2pm on Thursday, May 23, 2019 at One Exchange Plaza, Suite 620, Raleigh, NC 27601. Construction bids will be received until 2pm on Tuesday, June 11, 2019.
 

Lead Department:
Public Utilities

Right of Way Acquisition

Phase details coming soon.

Lead Department:
Public Utilities

Construction

Phase details coming soon.

Lead Department:
Public Utilities

Complete

Phase details coming soon.

Lead Department:
Public Utilities

History

The current water and sewer mains in these areas are aging. Water mains slated for replacement through this project are undersized. These mains do not meet current City of Raleigh design standards. The condition of the adjacent sewer mains were also evaluated for damage. Damage found in the current system scheduled for replacement or rehabilitation as needed.

Schedule

Date Activity
Fall 2018 Project Design Complete
Spring 2019 Permitting Complete
N/A Easement Acquisition Complete
Summer 2019 Project Bid Complete
Fall 2019 Project Construction Begins
Summer 2020 Project Construction Complete