Winthrop Drive

Transit, Streets, and Sidewalks

Winthrop Drive Sidewalk Project

We are installing a new sidewalk!

The Winthrop Drive Sidewalk Project is a product of a successful resident-initiated Raleigh Sidewalk Petition. The Raleigh City Council approved the project on May 1, 2018.

We are installing a sidewalk on the East side of the street from West Millbrook Road to Sleepy Hollow Drive.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
SA Hauling & Utilities

Contact

 

Brian Roth-Roffy, PE
Project Manager
 

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

We propose to install a 6-foot wide sidewalk placed 2.5-feet behind the curb. We will also install curb ramps and curb and gutter where needed. 

Next Steps

 

We are scheduled to advertise for construction bids this fall.

Phase Contacts

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Lead Department:
Engineering Services

Construction

Updated Aug. 18

Crews have finished construction on on Winthrop Drive and a project walk through is scheduled.

Next Steps

 

Complete Project 

Lead Department:
Engineering Services

Public Review of Project

The safety and security of our community is our top priority. The City of Raleigh is taking the spread of COVID-19 very seriously and canceled public meetings during this time, including the meeting regarding the Winthrop Drive Sidewalk Project.

Our goal is to keep City street and sidewalk projects on schedule, even in these difficult times. With this goal in mind, we sent letters to the affected property owners along the corridor and posted a short presentation and the project design map online for public review for two weeks.

Public comments and questions are an essential element of the design process; below are the results from the online survey and responses to general comments and questions we received. 

Public Survey Results
Responses to Comments 

 

Project Schedule

Date Description
April 2020 Public Review and Comment
Summer 2020 Easement Acquisitions Complete
Fall 2020 Advertise for Construction Bids
Winter 2021 Award Construction Contract
Spring 2021 Project Complete