Wildcat Branch Sanitary Sewer Improvements

Improvement project will replace aging materials to meet future infrastructure capacity demand.

Project will provide additional sanitary sewer infrastructure capacity to prevent damage and possible overflows identified during modeling from the 2020 10-year Storm Survey. This project will replace, parallel, and potentially re-route approximately 6,000 linear feet of existing 15-inch to 24-inch sanitary sewer line with new 30-inch sanitary sewer lines for Hammond Rd between Rush Street and the Walnut Creek Greenway Trail and between S Wilmington St and Hammond Rd, north of I-40.

Project Details

 
Type:
Water and Sewer
Project Lead:
Lorea Sample
Contractors:
Kimley - Horn & Associates

Contact

 

Lorea Sample
Senior Project Administrator
Phone: 919-996-3484 (Office)
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

This phase is complete.

Lead Department:
Water

Design

Project is currently in the design phase. More details to follow. 

Lead Department:
Water

Right of Way Acquisition

Check back for future details. 

Lead Department:
Water

Construction

Check back for future details.

Lead Department:
Water

Complete

Check back for future details.

Lead Department:
Water

History

Preliminary Engineering Report has been finalized.

Schedule

Date Activity
Winter 2022 Project Design Complete
Winter 2022 Permitting Complete
Fall 2022 Easement Acquisition Complete
Spring 2023 Project Bid Complete
Summer 2023 Project Construction Begins
Summer 2024 Project Construction Complete