Whittier Drive Sidewalk Project

We are installing a new sidewalk!

The Whittier Drive Sidewalk Project is the product of a successful Sidewalk Petition that the City received in the Fall of 2018.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
White Oak Construction

Contact

 

Molly Zahorian
Project Manager
 

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The project will install a five-foot-wide sidewalk along the east side of the street between Killington Drive and Optimist Park pool entrance.

Construction bids were opened in December 2020.

Next Steps

 

Bring construction bid to City Council for authorization.   

Lead Department:
Engineering Services

Construction

 

 A project walkthrough was completed in July.

 

Lead Department:
Engineering Services

Complete

Project is complete.

Lead Department:
Engineering Services

Schedule

Winter = January - March, Spring = April - June, Summer = July - September, Fall = October - December
Date Description
Jan. 6 Design Plans Public Meeting
Fall 2020 Construction bids
Winter 2021 Construction Starts
Summer 2021 Project Complete