Sanitary sewer pipes under the railroads on West Hargett Street were found to be in fair to poor condition following condition assessment. Due to the importance of keeping infrastructure under the railroad in good condition these pipes are being replaced.

Construction schedule is dependent on the railroad. Projects that involve railroads have additional requirements and the railroad provides a representative that must be on site during construction. Construction cannot begin until that representative is able to be on site.

Project Details

 
Type:
Water and Sewer
Budget:
$555,850
Project Lead:
Breanne Long
Contractors:
Moffat Piping

Contact

 

Breanne Long

Senior Project Manager

Email

919-996-3732 (Office)

 1 Exchange Plaza #620
Raleigh, NC 27601

Lead Department:
Water

Planning

This phase is complete. 

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

Project will begin construction when railroad is available. 

Lead Department:
Water

Complete

Project completion date is dependent on railroad availability.  

Lead Department:
Water

History

Construction contracts are currently routing. Current infrastructure found to be in poor condition. Replacement of aging material is deemed necessary to protect environment and property of residents.

Schedule

DATE ACTIVITY
SUMMER 2019 PROJECT DESIGN COMPLETE
FALL 2019 PERMITTING COMPLETE
N/A EASEMENT ACQUISITION COMPLETE
SUMMER 2019 PROJECT BID COMPLETE
Dependent on Railroad. PROJECT CONSTRUCTION BEGINS
Dependent on Railroad. PROJECT CONSTRUCTION COMPLETE