Water and Sewer

West Hargett Street

Sewer Line Replacement

Sanitary sewer pipes under the railroads on West Hargett Street were found to be in fair to poor condition following condition assessment. Due to the importance of keeping infrastructure under the railroad in good condition these pipes are being replaced.

This project seeks to avoid negative impacts to the environment by replacing these sewer lines before any negative environmental impacts can occur.

Project Details

 
Type:
Water and Sewer
Budget:
$555,850.00
Project Lead:
Breanne Long
Contractors:
Moffat Piping

Contact

 

Breanne Long
Senior Project Manager
Phone: 919-996-3732 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Planning

This phase is complete. 

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

Construction began in September 2020 and will continue through the end of November 2020.  

Lead Department:
Water

Complete

Project completion date is dependent on railroad availability.  

Lead Department:
Water

History

Construction contracts were routed. Current infrastructure found to be in poor condition. Replacement of aging material was deemed necessary to protect environment and property of residents.

Schedule

Date Activity
Summer 2019 Project Design Complete
Fall 2019 Permitting Complete
n/a Easement Acquisition Complete
Summer 2019 Project Bid Complete
Fall 2020 Project Construction Begins
Winter 2020 Project Construction Complete