Reynolds Road without sidewalk

Transit, Streets, and Sidewalks

Reynolds Road Sidewalk Project

We are installing a new sidewalk!

The Reynolds Road Sidewalk Project is the product of a successful sidewalk petition the City received in the winter of 2019.

We plan to install a five-foot-wide sidewalk with a three-and-a-half-foot setback from the curb along the south side of the street from Camelot Drive to Lambeth Drive.  

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction

Contact

 

Jacob Ray
Project Manager

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

Updated Sept. 23

Due to unforeseen circumstances, we are having to postpone the Sept. 23, scheduled meeting. Once a new date is established, we will post the information.

We do apologize for any inconvenience and look forward to meeting with you soon.

Thank you for your understanding.

City staff has completed the early design plans, and we plan to have a public meeting soon.

Next Steps

 
  • Finalize project schedule and post to website