Water and Sewer

Perry Creek Interceptor

Capacity Increase Project

This project will replace with a larger size or parallel the existing Perry Creek Interceptor to increase capacity. The alignment crosses I-540, Capital Boulevard, a railroad, and is in close proximity to Greshams Lake.

 

Project Details

 
Type:
Water and Sewer
Budget:
$1,000,000
Project Lead:
Breanne Long, PE

Contact

 

Breanne Long, PE
Senior Project Manager
Phone: 919-996-3732 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

There is survey and environmental work currently going forward for this project.

Lead Department:
Water

Design

Phase details coming soon.

Lead Department:
Water

Right of Way Acquisition

Phase details coming soon.

Lead Department:
Water

Construction

Phase details coming soon.

Lead Department:
Water

Complete

Phase details coming soon.

Lead Department:
Water

HISTORY

This project was identified by City of Raleigh staff as an area of potential SSO's. 

Sustainability

This project will upsize a sewer interceptor that could be at risk of SSO's (Sanitary Sewer Overflows) during wet weather in the near future. Upsizing this interceptor now will avoid those potential SSO's.

Schedule

Date Activity
Fall 2021 Project Design Complete
Fall 2021 Permitting Complete
Winter 2022 Easement Acquisition Complete
to be determined Project Bid Complete
to be determined Project Construction Begins
to be determined Project Construction Complete