Open_Cut_Pipe

Water and Sewer

Peace Street Utility Improvement Project

Improvement project will replace aging materials to meet future infrastructure capacity demand.

The project includes rehabilitating and replacement of deteriorating water and sewer pipes along Peace Street. Streets impacted by this project will not be left in disrepair after project is completed and will also be upgraded during a future City of Raleigh streetscape project. 

Project Details

 
Type:
Water and Sewer
Budget:
$629,473.00
Project Lead:
Raleigh Water
Contractors:
Pipeline Utilities, Inc.

Contact

 

Eileen Navarrete
Engineering Manager
Phone: 919-996-3480 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water
Service Unit:
Water Treatment

Subscribe

 

Planning

This phase is complete. 

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

Important Project Update:
The City’s contractor is concluding restoration work in the vicinity of West Peace Street and North Boylan Avenue. Work is shifting to the west side of the project to replace aging sewer infrastructure. The City of Raleigh will close the 900 and 1000 blocks of West Peace Street in Raleigh, NC, between Glenwood Avenue and West Johnson Street, on Monday, July 12. Closure will remain in effect Monday through Friday, 7 am through 7 pm. There will be no closures before or after these hours or on weekends. Project is expected to be completed by the end of July. Access to businesses and for local traffic will remain open.
 

Before

Before

After

After

Lead Department:
Water

Complete

Phase details coming soon.

Lead Department:
Water

History

Past CCTV footage found that current aging water infrastructure along Peace Street is in need of rehabilitation. Pipeline Utilities, Inc. was mobilized on-site to start construction. Work started at the intersection of Peace Street and Boylan Avenue on March 24, 2021. Work at that intersection now complete.

Schedule

Date Activity
Spring 2020 Project Design Complete
Summer 2020 Permitting Complete
n/a Easement Acquisition Complete
Fall 2020 Project Bid Complete
Spring 2021 Project Construction Begins
Summer 2021 Project Construction Complete