Update: Funding for the project will be appropriated in Summer of 2020. Project will be advertised for construction bids in Summer of 2020 with construction will beginning in the Fall of 2020.

This project is currently in the easement acquisition and permitting stage. The project includes approximately 10,000 linear feet of 24-inch water transmission main along Hebron Church Road and New Bethel Church Road in Garner.

Project Details

 
Type:
Water and Sewer
Budget:
$3,600,000
Project Lead:
Louis Bennet
Contractors:
CDM Smith

Contact

 

Louis Bennett
Senior Project Manager
Phone: 919-996-3504 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This project is currently in the design phase along with easement acquisition and permitting. 

Lead Department:
Water

Construction

Project scheduled to begin construction in Spring 2020. 

Lead Department:
Water

Complete

Project scheduled to be completed in Spring 2021.

Lead Department:
Water

History

This project was identified in the Water System Master Plan as a capacity upgrade need in the 532-pressure zone found in Garner, NC.

Schedule

Date Activity
Summer 2018 Project Design Complete
Summer 2019 Permitting Complete
Summer 2020 Easement Acquisition Complete
Summer 2020 Project Bid Complete
Fall 2020 Project Construction Begins
Fall 2021 Project Construction Complete