Old Deer Trail

Transit, Streets, and Sidewalks

Old Deer Trail Sidewalk Project

We are installing a new sidewalk!

The Old Deer Trail sidewalk project was initiated as a City of Raleigh Sidewalk Petition.

We will install a 5-foot sidewalk placed 3.5 feet from the back of the curb from Mourning Dove Road to just north of Apple Orchard Way.

There may be adjustments to the sidewalk to avoid major impacts in certain areas as needed and determined by our engineering staff.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
JSmith Civil, LLC

Contact

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

We will install a 5-foot sidewalk placed 3.5 feet from the back of the curb from Mourning Dove Road to just north of Apple Orchard Way.

There may be adjustments to the sidewalk to avoid major impacts in certain areas as needed and determined by our engineering staff.

Next Steps

 

The project is out for construction bids, and construction is scheduled to start in late spring or early summer 2020.

Phase Contacts

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Lead Department:
Engineering Services

Construction

Updated Oct. 8

The project has been combined with other sidewalk projects on Centennial parkway and Raleigh Boulevard for construction. Our construction contractor, JSmith Civil, will begin work mid to late-September and should be completed with all three sidewalks by Dec. 2020. The work will take place during business hours from 7 a.m. to 6 p.m., Monday thru Friday, and may include some Saturday work.

We will make every effort to minimize any inconvenience during construction and greatly appreciated your patience and cooperation.

Next Steps

 

 

  

Phase Contacts

 

Cordis Yates-Thompson
Project Manager
919-996-4055

Lead Department:
Engineering Services

Construction Information

Meet the Construction Team:

City Project Manager: Cordis Thompson

City Inspector: AJ Mitchell

Construction Contractor: JSmith Civil, LLC

What to Expect During Construction:

Construction is expected to take three months;

Work hours are between 7:00 a.m. and 6:00 p.m. Monday – Friday;

Lane closures with flagging operations (between 9:00 a.m. and 4 p.m. only);

Access to properties and emergency services shall be maintained at all times;

City will notify residents of any possible access disruption, and;

All disturbed areas will be reseeded and restored after contraction is complete.

Project Schedule

Date Description
Feb. 2020 Project to Construction Bid
April 2020 City Council to Authorize Construction Contract
Aug. 2020 Start Construction
Dec. 2020 Project Complete