Oberlin Road Waterline Improvements

Improving system capacity and water flow.

Project will replace an existing 8-inch waterline with a 12-inch waterline to improve water flow and system resiliency. Project limits are Oberlin Road from Bedford Avenue north to Davis Street.

Project Details

 
Type:
Water and Sewer
Budget:
$4,200,000
Contractors:
Carolina Civilworks, Inc.

Contact

 

Janeen Goodwin, PE
Senior Project Administrator
Phone: 919-996-3494 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Right of Way Acquisition

This phase is complete.

Lead Department:
Water

Construction

All water and sewer line installation and service connections are complete on Oberlin Road. Paving restoration is also complete on Oberlin Road from Fairview Road to Wade Avenue and the road closure has been reopened to all traffic.

To complete the project, a water valve and vault installation located near Annapolis Drive and Wade Avenue will begin work January 3, 2022. This planned work will require closure of the Wade Avenue Westbound ramp off northbound Oberlin Road and the Oberlin Road North exit ramp/Annapolis Drive from westbound Wade Avenue for approximately 3 weeks. Detours will be in place to direct traffic. Please be aware of all posted traffic signs, detours, traffic cones, and work crews.

Thank you for your patience during these infrastructure improvements.

Press Release

The contractor is required to maintain access to businesses and residences at all times.

  

Lead Department:
Water

Complete

This phase is scheduled.

Lead Department:
Water

History

Water improvements were identified for this area due to water pressure and system resiliency needs in the past few years. The project contractor is Carolina Civilworks and construction work began in January 2021. Waterline replacement work has been completed from Bedford Road to Van Dyke Avenue.

Schedule

Date Activity
Spring 2020 Project Design Complete
Summer 2020 Permitting Complete
n/a Easement Acquisition Complete
Fall 2020 Project Bid Complete
Winter 2021 Project Construction Begins
Spring 2022 Project Construction Complete