Stream erosion on Noel Court

Stormwater

Noel Court Streambank Stabilization

Drainage Assistance Program

A stream connected to House Creek is severely eroded. Erosion is within 12 feet of a property on Noel Court. We are looking to repair the stream and stabilize it's banks. This will protect the stream and the house on this property.

 

Project Details

 
Type:
Stormwater
Budget:
$225,000
Project Lead:
Stormwater Management
Contractors:
Timmons Group (Design)

Contact

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Design

This part of the project is on hold until we finalize details for the easements required for the project. Once we work through those details, the design will continue. 

Design Details (Pending)

The goal is to stabilize about 80 feet of the left side of the stream by: 

  • Adding rock boulders; 
  • Improving the slope; and, 
  • Re-planting the area. 
Severely eroded streambanks near a house on Noel Court.

Severely eroded streambanks near a house on Noel Court. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Construction

More details coming soon. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Complete

More details coming soon. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Date Activity
July 2020 Project planning began
Pending Project design complete
TBD Project construction begins
TBD Project construction complete