Neuse River Resource Recovery Facility Return Activated Sludge Project

Replacement of infrastructure found on-site at facility to prepare for future system demands.

This project consists of replacement of nine existing return activated sludge screw pumps. There are three screw pumps at three cell locations found on-site. Also, project will cover all associated electrical upgrades along with repairs to concrete structures and railings. The replacement of the screw pumps will improve the efficiency of the wastewater treatment process and provide a more reliable system for community use.

Project Details

 
Type:
Water and Sewer
Budget:
$4,300,000
Project Lead:
Todd Toler
Contractors:
Heron

Contact

 

Todd Toler
Senior Engineer
Phone: 919-996-3476 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Design

This phase is complete.

Lead Department:
Water

Right of Way Acquisition

This phase is not needed.

Lead Department:
Water

Construction

Project is currently in this phase. Contractor is Heron. Grouting for first trough scheduled for Spring 2021. Work on second screw pump is nearing completion.

Lead Department:
Water

Complete

Phase details will be added when available. 

Lead Department:
Water

History

The Neuse River Resource Recovery Facility Return Activated Sludge Screw Pump Replacement Project was identified in the Sustainable Infrastructure and Asset Management Program Assistance Program as an asset in poor condition and in need of upgrade to help the city safely process wastewater. Contract was awarded to Heron. The contractor ordered the nine stainless steel screw pumps and expected to take delivery of the first three screw pumps in Fall of 2020. Pre-construction meeting held week of December 1, 2020. Mobilization of work crews occurred week of Dec 7, 2020. First set of screw pumps delivered end of 2020. First set of screw pumps completed. 

Schedule

Date Activity
Fall 2019 Project Design Complete
Fall 2020 Permitting Complete
n/a Easement Acquisition Complete
Winter 2020 Project Bid Complete
Fall 2020 Project Construction Begins
Fall 2021 Project Construction Complete