Milburnie Road Traffic Calming Project

Transit, Streets, and Sidewalks

Milburnie Road Traffic Calming Project

Improving safety, mobility, and connectivity for pedestrian, bicycle, and vehicular traffic

We are installed traffic calming devices and replacing old sewer mains on Milburnie Road from Colleton Road to Chatham Lane. Improvements along the roadway include:

  • Bike lanes;
  • New bus stop pads with benches, wastebaskets, and shelters at some locations;
  • Bump outs with landscaping;
  • Pedestrian crossing medians;
  • Stormwater upgrades; and,
  • A bioretention basin.

Project Details

 
Type:
Streets
Project Lead:
Roadway Design & Construction
Contractors:
Moffat Pipe Inc.

Contact

 

Sean Driskill, PE
Project Manager
919-996-4106

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Construction

The contractor is scheduled to finish planting along the corridor this fall. 

Next Steps

 

The City will resurface and install new pavement markings in the Summer of 2020.

Phase Contacts

 

Sean Driskill, PE
Project Manager
919-996-4106

Lead Department:
Engineering Services

Complete

We finished the traffic calming installation along the corridor in fall 2019. 
The City is scheduled to resurface and install the new pavement marking in the summer of 2020.

Lead Department:
Engineering Services

History

Traffic Calming Projects are projects that the Neighborhood Streetscape Program have passed onto our department. We complete engineering designs and manage the construction of these projects.

The goal of the Neighborhood Streetscape Program is to improve street safety for:

  • Motorists;
  • Pedestrians;
  • Bicyclists; and,
  • Improve the living conditions for residents along a street.

Treatments to the street enhance the appearance and slow down motor-vehicle traffic.

Schedule

Date Activity
Fall 2019 Construction Complete
Late Fall 2019 Landscaping Complete
Late Fall 2019 Construction Contract Complete
Summer 2020 City to Repave Roadway
Late Fall 2020 Warranty Complete

Related Projects