a section of Louisburg Road, shows no sidewalk on either side of the road.

Transit, Streets, and Sidewalks

Louisburg Road (US 401) Sidewalk project

We are dedicated to making Raleigh a more walkable City!

We’re installing a sidewalk along the west side of Louisburg Road. The project fills in several gaps in sidewalks along the corridor to provide connectivity from Spring Forest Rd to Perry Creek Rd. Pedestrian signals will also be installed at several existing signalized intersections.

Project Details

 
Type:
Bicycle and Pedestrian
Budget:
$1.3 Million
Project Lead:
Roadway Design & Construction

Contact

 

Chad Cantrell, PE
Project Manager
919-996-4173

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

Updated June 9

We are installing approximately 6,500 feet of sidewalk along Louisburg Road. The project fills in gaps in the sidewalk along the corridor to provide connectivity from Spring Forest Road to Perry Creek Road and installs new pedestrian crossing signals at the I-540 intersection. 

Lead Department:
Engineering Services

Right of Way Acquisition

Updated June 9

We are now in the right of way and easement acquisition phase of the project. Survey teams are placing right of way and temporary easement stakes along the corridor and members of the Real Estate team are reaching out to property owners. 

Next Steps

 

Advertise for construction contracts 

Lead Department:
Engineering Services

Schedule

Activity Date
Complete Right of Way and Easement Acquisition Summer 2021
Advertise for Construction Bids Early Fall 2021
Start Construction Fall 2021
Project Complete Summer 2022