Water and Sewer

Lenoir Street Sewer Replacement

Improvement project will replace aging materials to meet future infrastructure capacity demand.

Sanitary sewer pipe replacement project at the Lenoir Street Park. Replacement of roughly 200 Linear Feet of 10” sanitary sewer pipe.

Project Details

 
Type:
Water and Sewer
Budget:
$70,000.00
Project Lead:
Louis Bennet
Contractors:
Withers Ravenel

Contact

 

Louis Bennett
Senior Project Manager
Phone: 919-996-3504 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Pre-Approval

This phase is complete.

Lead Department:
Water

Programmed

This phase is compete. 

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Right of Way Acquisition

This phase is complete.

Lead Department:
Water

Construction

Construction scheduled to begin February 2021. Expected completion within 4 weeks. Project construction schedule may vary due to weather or other unexpected events.
Lenoir Street Park will be closed during this phase.

Lead Department:
Water

Complete

Phase details coming soon. 

Lead Department:
Water

History

Sewer lines found in Lenoir Street Park were designated for replacement in the annual infrastructure report. Advertised for construction bids in Summer 2020. Awarded to Precision Earth and Pipe, Inc  

Schedule

Date Activity
Fall 2019 Project Design Complete
Fall 2019 Permitting Complete
Winter 2019 Easement Acquisition Complete
Summer 2020 Project Bid Complete
Winter 2021 Project Construction Begins
Winter 2021 Project Construction Complete