Lake Boone Trail Road before Construction

Transit, Streets, and Sidewalks

Lake Boone Trail Sidewalk Project

We are working to providing consistent pedestrian access along this roadway

We are installing about 350 ft. of sidewalk on the south side of Lake Boone Trail. The new sidewalk will start at Blue Ridge Road and runs to the entrance of Rex Woods Office Center. The project will fill in one of the last remaining gaps on Lake Boone Trail, providing consistent pedestrian access.

We will also upgrade all the sidewalk ramps at the intersection of Blue Ridge Road and Lake Boone Trail. New pavement markings at this intersection will also provide high-visibility crosswalks.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
Browe Construction

Contact

 

Grady McCollum, PE
Project Manager
919-996-4106

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

Updated June 2020

The design plans are complete, and the project is advertised for construction bids.

Lead Department:
Engineering Services

Construction

The project is complete.  

 

Next Steps

 

 

 

Lead Department:
Engineering Services

Complete

June 15, 2021

The project is complete.

Lead Department:
Engineering Services

Schedule

Date Activity
Summer 2020 Advertise for Construction Bids
December 2020 Start Construction
Spring 2021 Project Complete