Holston Lane

Transit, Streets, and Sidewalks

Holston Lane Sidewalk Project

We are installing a sidewalk.

We are working on making Raleigh a more walkable City. This City project will install a sidewalk on the north side of Holston Lane between Sunnybrook Road and Calumet Drive.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
SA Hauling & Utilities

Contact

 

Brian Roth-Roffy, PE
Project Manager
 

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

We are complete with the design of this project, and will advertise for construction bids in the winter of 2020. 

Next Steps

 

The project is scheduled to advertise for construction bids in early 2020.  We will package this project with sidewalk projects on Ileagnes Road, Raleigh Boulevard, and Centennial Parkway.

 

 

 

Lead Department:
Engineering Services

Construction

Updated June 2

The project has been combined with other sidewalk projects on Barksdale Drive and Winthrop Drive for construction. 

Crews are scheduled to start construction in June along Holston Drive.

Next Steps

 

Start construction in June.