hillock drive stormwater system

Water and Sewer

Hillock Drive Drainage Improvements

Drainage Assistance Program

Two properties on Hillock Drive flood during heavy rainstorms. The stormwater pipes in the area are too small and cannot handle the amount of runoff that flows through the system.

Project Details

 
Type:
Stormwater
Budget:
$305,000
Project Lead:
Stormwater Management

Contact

 

Dale Hyatt, PE
Drainage Assistance Program Manager
919-996-4071

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

We looked at several options to address flooding on Hillock Drive. It will cost the same to replace the pipes as it will to acquire the property. 

After ongoing discussion with residents, we:

  • Purchased the properties; and,
  • Will be demolishing the structures to eliminate flooding risks. This will be done in December. 

We are also exploring options for future uses of the properties. 

Phase Contacts

 

Dale Hyatt, PE
Drainage Assistance Program Manager
919-996-4071

Lead Department:
Engineering Services

Schedule

Date Activity
February 2019 Project planning and design phase
August 2019 Project design complete
May 2020 Property acquisition
December 2020 Demolition of two structures
Ongoing Exploring future use of the property