rendering of new fire station six

Safety

Fire Station 6 Replacement

Updating City Facilities

We are replacing the fire station on Fairview Road. The station is temporarily relocated to Fire Station 5 at 300 Oberlin Road. 

Project Details

 
Type:
City Properties and Facilities
Budget:
$5.5 million
Project Lead:
Construction Management
Contractors:
Pro Construction

Contact

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services
Participating Department:
Fire
Service Unit:
Constructing City-owned Buildings

Programmed

This phase is complete. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Construction

Construction is more than 95 percent finished! The contractor has completed most of the interior and exterior work for the building. They are now working on: 

  • Electrical;
  • Plumbing;
  • Painting; and, 
  • Exterior brick pavers.

The schedule shifted - We're now expected to finish work in the fall.

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2016 Project design complete
Summer 2017 Project construction begins
Fall 2020 Project construction complete

Renovations

The new fire station will be 14,990 square feet with two bays for equipment. Renovations include structural, electrical, interior, and landscaping work.