A rendering of fire station 22 replacement

Safety

Fire Station 22 Replacement

Updated City Facilities

We replaced the fire station on Durant Road. This station houses our hazard material unit and provides services to residents in north Raleigh. 

Project Details

 
Type:
City Properties and Facilities
Budget:
$9 million
Project Lead:
Construction Management
Contractors:
Davis Kane Architects (Design); Monteith Construction (Construction)

Contact

 

Alexander Shapiro
Project Manager
919-996-5589

 

Lead Department:
Engineering Services
Participating Department:
Fire

Subscribe

 

Programmed

This phase is complete. 

Phase Contacts

 

Danny Bowden, PE, MPA
Project Manager
919-996-5583

Stephanie Seeber, PA, AIA
Project Manager
919-996-5579

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Danny Bowden, PE, MPA
Project Manager
919-996-5583

Stephanie Seeber, PA, AIA
Project Manager
919-996-5579

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Construction

Construction is complete!

 

Next Steps

 

This month, the contractor will finish the internal punch list items, complete owner training on the use of various systems, obtain the remaining inspections, and receive the Certificate of Occupancy.   

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Complete

The project is complete!

The Fire Department moved into the station on August 2. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2018 Project design began
Summer/Fall 2020 Building permit approval; Pre-qualification process for sub-contractors
Fall 2020 Project design complete; CMAR bid process complete
Winter 2021 Project construction begins
Spring 2022 Project construction complete

Back side of Fire Station 22

Windows were added to the new fire station in January 2022.

Windows were installed on the side of the fire station in January. 

Back side view of Fire Station 22. 

The ceiling grid was installed.

Outside of the new Fire Station 22 (under construction - Dec. 2021)

Concrete exterior of the new Fire Station 22 while under construction.

The concrete frame for the new fire station 22 building that's under construction.

Exterior of Fire Station 22 early in the construction phase. 

Background

This fire station was originally built as a two-company station for an engine and aerial apparatus. We will be replacing the station at the same time that the North Carolina Department of Transportation's (NCDOT) project to separate an intersection of the railroad in this area.

What is a CMAR?

CMARs coordinate with the general contractor and the design team for a project. Working together early in the process reduces risk with constructing a final design. The CMAR for this project will help carryout design and construction specifications in a timely and cost-effective manner to streamline the construction phase.