Rendering of Fire Station 14 Replacement

Safety

Fire Station 14 Replacement

Updating City Facilities

We are replacing the fire station to the meet the needs of the growing service area. The station is moving from Lake Boone Trail to Harden Road. 

Project Details

 
Type:
City Properties and Facilities
Budget:
$9.5 million
Project Lead:
Construction Management
Contractors:
Stewart Cooper Newell Architects (Design); Pro Construction (Construction)

Contact

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services
Participating Department:
Fire
Service Unit:
Constructing City-owned Buildings

Programmed

This phase is complete.

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Planning

This phase is complete.

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Construction

We are almost 80 percent finished with construction! The contractor is working on: 

  • Heating and cooling units; 
  • Window installation; 
  • Flooring; 
  • Adding a protective fence at the top of the retaining wall; 
  • Curb and gutter; and,
  • Paving. 

The construction schedule shifted - Work is now expected to be finished in early 2021. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Alexander Shapiro
Project Manager
919-996-5589

Lead Department:
Engineering Services

Schedule

Date Activity
Summer 2016 Project design began
Fall 2017 Project design complete
Summer 2018 Project construction began
Winter 2021 Project construction complete

Renovations

The new station will be about 18,100 square feet with three bays for equipment including a: 

  • Ladder truck
  • Engine truck
  • Chief vehicles