new stormwater system on everett avenue

Water and Sewer

Everett Avenue Drainage Improvements

We installed a new stormwater pipe on Everette Avenue between Brooks Avenue and Gardner Street. 

Project Details

 
Type:
Stormwater
Budget:
$136,000
Project Lead:
Stormwater Management
Contractors:
McQueen Construction

Contact

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services
Service Unit:
Stormwater

Pre-Approval

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Design

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Construction

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Complete

We finished construction! The new pipe will address flooding issues at 2720 Everett Avenue. Before construction - the property experienced street and garage flooding. The new pipe also brings the stormwater system up to current standards.

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

stormwater construction on everett avenue

Schedule

Date Activity
August 2018 Project planning and design phase
January 2019 Project design complete
October 2019 Project construction began
November 2019 Project construction complete