East Neuse River Construction Equipment

Water and Sewer

East Neuse Regional Pump Station Project

Current Activity: Excavation has begun for the 50-foot deep pump station along with the installation of twin 72-inch sewer lines. The installation of these lines will be located below the Neuse River provided that the river is flowing at normal levels. A temporary construction access road will be located on the north side of the river.

 

  

Project Details

 
Type:
Water and Sewer
Budget:
$51,619,000
Contractors:
CDM Smith

Contact

 

Perry Allen, PE
Engineering Supervisor
Phone: 919-996-3466 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Pre-Approval

This phase is complete

Lead Department:
Water

Programmed

This phase is complete. 

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Right of Way Acquisition

This phase is complete.

Lead Department:
Water

Construction

This project is currently in the construction phase. 

Lead Department:
Water

Complete

Phase details coming soon. 

Lead Department:
Water

History

The proposed East Neuse Interceptor will divert flow from the Neuse River drainage basin directly to the East Neuse River Pump Station. This will relieve the demands on the existing Crabtree and Walnut Creek Lift Stations. The East Neuse River Pump Station will also receive excess flows upstream of the Walnut Creek Pump Station. The combination of the East Neuse River Pump Station and the East Neuse Interceptor provide an alternative option for managing large portions of the sanitary sewer flow to the Neuse River Resource Recovery Facility should problems arise with the Walnut Creek Lift Station and associated pump stations.

Schedule

Date Activity
Summer 2019 Project Design Complete
Summer 2019 Permitting Complete
Fall 2019 Easement Acquisition Complete
Summer 2019 Project Bid Complete
Fall 2019 Project Construction Begins
Summer 2022 Project Construction Complete