ENRPS-North

Water and Sewer

East Neuse Regional Pump Station Improvement Project

Project will relieve wastewater flow demands from the Crabtree and Walnut Creek lift stations.

The East Neuse Interceptor project will divert flow from the Neuse River drainage basin directly to the East Neuse River Pump Station. This will relieve the demands on the existing Crabtree and Walnut Creek Lift Stations. The East Neuse River Pump Station will also receive excess flows upstream of the Walnut Creek Pump Station. The combination of the East Neuse River Pump Station and the East Neuse Interceptor provide an alternative option for managing large portions of the sanitary sewer flow to the Neuse River Resource Recovery Facility should problems arise with the Walnut Creek Lift Station and associated pump stations. This project consists of the construction of a new 102 Million Gallons per Day (MGD) wastewater and wet weather pump station that will serve as the backbone to the City’s wastewater collection system in addition to accommodating wet weather flows.

 

  

Project Details

 
Type:
Water and Sewer
Budget:
$51,808,000
Project Lead:
Raleigh Water
Contractors:
TA Loving Company

Contact

 

Perry Allen, PE
Engineering Supervisor
Phone: 919-996-3466 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Pre-Approval

This phase is complete

Lead Department:
Water

Programmed

This phase is complete. 

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Right of Way Acquisition

This phase is complete.

Lead Department:
Water

Construction

Construction is approximately 95% complete. Final completion is scheduled for Winter 2023. Current major activities involve final site grading and concrete paving around the pump station exterior. Protective coating application continues in the wet wells. HVAC equipment and ductwork installation continue throughout the pump station. Installation of stainless steel mechanical bar screens is completed. Continuing installation of the Troughing Conveyor equipment. Continuing installation of the Odor Control System.  Electrical contractor continues the installation of exposed conduit and associated wiring in the Electrical Room, Dumpster Room, and Screening Room.

Neuse_Pump_Station_Build

Pump station build at 58 feet below grade.

Neuse_Pump_Station_Build

Northeast Pump Station Wall Build

Project_Back_Fill

Drone picture of project backfill phase.

Project_Back_Fill_NW

Drone picture of project backfill phase.

Neuse_Pump_Station_Build

Drone Progress Photo

Neuse_Pump_Station_Build

Drone Progress Photo

Odor_Control_Tower

Odor Control Tower Installation

Screening Room

Screening Room

Screening Room

Electrical Room

Project Site North View

Project Site North View

Project Site South View

Project Site South View

Project Site Drone View

Project Site Drone View

ENRPS-North

Updated North View

ENRPS-South

Updated South View

ENRPS-West

Updated West View

Lead Department:
Water

Complete

Phase details coming soon. 

Lead Department:
Water

History

This project is funded to meet the demands of future regional wastewater processing. 

Schedule

Date Activity
Summer 2019 Project Design Complete
Summer 2019 Permitting Complete
Fall 2019 Easement Acquisition Complete
Summer 2019 Project Bid Complete
Fall 2019 Project Construction Begins
Winter 2023 Project Construction Complete