River-Pump-Station-Construction

Water and Sewer

East Neuse Regional Pump Station Improvement Project

Project will relieve wastewater flow demands from the Crabtree and Walnut Creek lift stations.

The East Neuse Interceptor project will divert flow from the Neuse River drainage basin directly to the East Neuse River Pump Station. This will relieve the demands on the existing Crabtree and Walnut Creek Lift Stations. The East Neuse River Pump Station will also receive excess flows upstream of the Walnut Creek Pump Station. The combination of the East Neuse River Pump Station and the East Neuse Interceptor provide an alternative option for managing large portions of the sanitary sewer flow to the Neuse River Resource Recovery Facility should problems arise with the Walnut Creek Lift Station and associated pump stations.

 

  

Project Details

 
Type:
Water and Sewer
Budget:
$51,619,000
Contractors:
CDM Smith

Contact

 

Perry Allen, PE
Engineering Supervisor
Phone: 919-996-3466 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Pre-Approval

This phase is complete

Lead Department:
Water

Programmed

This phase is complete. 

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Right of Way Acquisition

This phase is complete.

Lead Department:
Water

Construction

Construction is approximately 67% complete with final completion scheduled for Summer 2022. Major activity at this time involves concrete construction of the underground portion of the pump station which is approximately 58 feet below finished grade. Excavation has begun for the 50-foot deep pump station along with the installation of twin 72-inch sewer lines. The installation of these lines will be located below the Neuse River provided that the river is flowing at normal levels. A temporary construction access road will be located on the north side of the river.

Neuse_Pump_Station_Build

Pump station build at 58 feet below grade.

Neuse_Pump_Station_Build

Northeast Pump Station Wall Build

Project_Back_Fill

Drone picture of project backfill phase.

Project_Back_Fill_NW

Drone picture of project backfill phase.

Lead Department:
Water

Complete

Phase details coming soon. 

Lead Department:
Water

History

This project is funded to meet the demands of future regional wastewater processing. 

Schedule

Date Activity
Summer 2019 Project Design Complete
Summer 2019 Permitting Complete
Fall 2019 Easement Acquisition Complete
Summer 2019 Project Bid Complete
Fall 2019 Project Construction Begins
Summer 2022 Project Construction Complete