A view of the repaired stream on Doverton Court.

Stormwater

Doverton Court Streambank Stabilization

Drainage Assistance Program

There is severe streambank erosion at a property on Doverton Court. We will be repairing about 90 feet of the streambank to minimize impacts to the home. 

Project Details

 
Type:
Lakes, Streams, and Dams
Budget:
$143,000
Project Lead:
Stormwater Management
Contractors:
Timmons Group (Design); North State Environmental (Construction)

Contact

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Design

This phase is complete.

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Construction

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Complete

Construction for this project is complete! Crews worked on: 

  • Removing an old dam; 
  • Repairing eroded streambanks in two locations; and, 
  • Replacing a metal stormwater pipe that cannot handle the amount of stormwater flowing in this area. The pipe was replaced with a larger, reinforced concrete pipe.

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

The stream on Doverton Court before construction.

The stream on Doverton Court after construction. 

Schedule

Date Activity
August 2019 Project planning and design phase
July 2020 Project design complete
March 2021 Project construction begins
April 2021 Project construction complete

Background

The project was originally identified in 2016. At that time, the streambank erosion was about 15 feet from the home on Doverton Court. Since then, we've reprioritized the project based on the stream's condition.