The project consists of the following major construction items:
•Installation of approximately 560 linear feet of 6-inch to 12-inch diameter waterlines.
•Installation of approximately 4,900 linear feet of 8-inch to 10-inch sewer lines.
•Installation of approximately 1,600 linear feet of 8-inch sewer 'Cured In Place Pipe' liner.
•Replacement of existing active sewer laterals connected to sewer lines to be replaced along with installation of new sewer laterals.
•Reconnection of existing fire services.
•Grading, paving, erosion control, site cleanup, and seeding.

Project Details

 
Type:
Water and Sewer
Budget:
$3,333,895
Project Lead:
Todd Toler
Contractors:
JF Wilkerson Contracting Co., Inc.

Contact

 

Todd Toler
Senior Engineer
Phone: 919-996-3476 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

Project phase is complete.

Lead Department:
Water

Design

Project phase is complete. 

Lead Department:
Water

Construction

Water and sewer lines are being replaced between S. Bloodworth Street and S. East Street. The water and sewer will be replaced along Davie Street in preparation for street resurfacing between S. Wilmington Street and S. Tarboro Street which is scheduled to start Summer 2022. 

Traffic Impacts:
Raleigh Water will conduct a full closure of the intersection of Davie Street and Chavis Way and the 500 Block of Davie Street between South East Street and Chavis Way in Raleigh NC, at 7:00 AM, Monday, April 25, 2022, for a water and sewer improvement project. Closure is expected to last until 7:00 PM, Friday, May 20, 2022. Parking restrictions will be enforced in designated areas.

Raleigh Water will conduct a full closure of the intersection of Davie Street and South Swain Street, including the 500 Block of Davie Street between Chavis Way and South Swain Street in Raleigh NC, at 7:00 AM on Monday, May 9, 2022, for a water and sewer improvement project. Closure is expected to last until 7:00 PM Friday, May 27, 2022Parking restrictions will be enforced in designated areas.

Raleigh Water will conduct a full closure of the intersection of Davie Street and South Blount Street, the 100 Block of Davie Street between South Wilmington Street and South Blount Street and the 200 block of Davie Street between South Blount Street and South Person Street in Raleigh NC, at 7:00 AM on Monday, May 16, 2022, for a water and sewer improvement project. Closure is expected to last until 7:00 PM Friday, June 3, 2022. Parking restrictions will be enforced in designated areas.

Lead Department:
Water

Complete

Check back for phase details. 

Lead Department:
Water

History

Water and sewer lines are being replaced between S. Bloodworth Street and S. East Street.

Schedule

Date Activity
Fall 2021 Project Design Complete
Fall 2021 Permitting Complete
N/A Easement Acquisition Complete
Fall 2021 Project Bid Complete
Spring 2022 Project Construction Begins
Winter 2022 Project Construction Complete