white oak lake before

Water and Sewer

White Oak Lake Reconstruction

Lake Project

This privately owned lake has a failing spillway that controls the flow of water from the dam.

 

Project Details

 
Type:
Lakes, Streams, and Dams
Budget:
TBD
Project Lead:
Stormwater Management
Contractors:
Dewberry (Design)

Contact

 

David Kiker, PE
Project Manager
919-996-4074

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

We are no longer moving forward with this project. There were challenges getting required easements. NCDOT is also in the process of breaching the dam to meet regulatory requirements.

Phase Contacts

 

David Kiker, PE
Project Manager
919-996-4074

Lead Department:
Engineering Services

History

This project was initially part of a multi-phased project to reduce flooding and improve water quality in the Simmons Branch watershed.

We also fixed the stormwater system at:

  • Ravenwood Drive
  • Haplan Drive
  • Lail Court
  • Swift Drive
  • Pineview Drive

Schedule

Date Activity
Spring 2017 Stormwater models finalized, 70 percent of the project design plan developed, and environmental permits submitted
Fall 2017 Recommended design alternative presented
Late Fall 2018 Private utility relocation, permitting complete
Winter 2019 First project design complete
N/A Project construction phase